Before the K1 is moved by road to Carnforth it will be doing 3 more days work on the GCR.

The loco will work another photo charter then an evening diner on the 14th Feb and service trains on the 15th and 16th.

The move to Carnforth is planned for the 19th Feb. The first working party of the second stage of this year's winter maintenance will be on Saturday 22nd Feb when we will be removing the concrete arch and the side rods (ahead of tyre turning). The loco is booked onto West Coast's ground lathe on the 24th.