North Eastern Locomotive Preservation Group

  • Increase font size
  • Default font size
  • Decrease font size
K1 Blog

A blog of activities associated with the K1 62005.



18th February

Print

We had a pretty good couple of days last weekend. The valve crossheads were trial fitted following the adjustments made to correct the valve alignment problem.

The LH crosshead, after further minor adjustment was a satisfactory fit which enabled the LH valve to be refitted (after cleaning the valve rings and final cleaning of the heads). The RH crosshead requires a bit more work but should be ready for its final fit by next weekend.

Progress was also made in fitting the new lifting blocks by carefully truing the radius rod lifting block bearing surfaces. Final fitting of the blocks is now very close.

A number of reassembly preparation jobs were carried out and one rocking grate firebar was changed.

The outer wrapper repair is progressing well and is likely to be completed late this week/early next. Whilst the repair will be mag particle and ultrasonically tested shortly after completion the required hydraulic and steam tests will not be undertaken until the end of March to fit in with the rest of the winter work.

 

 

11th February

Print

We had a decent day on Saturday. By the time we left, a little later than usual, the loco was in a fit state to be moved with the hornstays and springs refitted to the leading wheelset. We did not have time to get the brake pull rods or the lub pipes back on but we should sort them this weekend.

Work to repair/renew the blower ring brackets, replace the blower pipe bracket and refurbish the primary screen fixed top rail were also completed.

On the coach the guard's compartment has now been undercoated apart from the outer door which is in need of repair (Chris Henwood's uncle has kindly agreed to do this).

Unfortunately there was no working party on Tuesday as no one volunteered.

The repair work to the outer wrapper has not started yet as we are waiting for final insurance co approval but this will hopefully come through shortly. The loco is however now in the repair shed and work will start as soon as the approval comes through.

We are doing another full weekend this Saturday and Sunday (you could do either day or both) and we really do need to get some mid week working parties on the go - I am not panicking yet but it is only a matter of time.

 

 

5th February

Print

We had a good couple of days last weekend with 7 of us there on Saturday and 4 on Sunday. Many thanks to all who took part.

Thanks too to all who offered to go and look after John Graham and the insurance co on Monday.

Over the weekend progress was made with a few smaller jobs and after a bit of a fight with the valve extracting gear both piston valves were removed. The rings were removed from the heads and the heads cleaned.

The back valve covers were also removed and cleaned and the liners were cleaned. The back covers were then refitted and the valves temporarily replaced without their rings.

This allowed the alignment to be checked and adjustments to the valve crossheads are now being made.

Since the weekend the insurance co have inspected the area of the firebox outer wrapper to be repaired and the new plate will hopefully be fitted over the next two weeks. The leading coupled wheelset is now back under the loco (fitted by West Coast on Tuesday) and this Saturday's main job will be refitting hornstays, springs, lub pipes and brake pull rods.

 

 

 

28th January

Print

We had a mixed day on Saturday. Progress was made on a number of jobs but owing to problems with the piston valve extractor the valves have still not been removed.

It was good to be joined by 4 of the Juniors who not only got stuck in with some useful work but seemed to enjoy the many attractions that Carnforth has to offer. (Photos on Juniors page)

After closer inspection we have decided to re-metal the RH leading coupled axlebox (we were just going to do the boss face) and the defective boiler plate work has now been removed. Our insurance co wish to examine the boiler with the platework removed before West Coast complete the repair.

Unfortunately I only had one response for a mid week working party so it has been cancelled but I am very grateful to Neil Smedley who has agreed to organise the acquisition, fitting and testing of the new cooker for the support coach. We might have someone to do the joinery repairs to the coach too.

As the programme has slipped a little with the problems with extracting the valves and the lack of mid week working parties, we are doing another full weekend this coming Saturday and Sunday. I also hope we can do a mid week working party next Tuesday.

 

21st January

Print

We had a good day on Saturday with completion of the annual backhead valve checks/maintenance, removal of the reach rod to facilitate the outer wrapper repair and the cleaning, measurement, stripping down and checking of the leading coupled axleboxes (West Coast removed the wheelset for us last week). Rolly also managed to make some progress with decorating the guard's compartment in the coach. Not a bad effort for 4 people.

 

17th January

Print

We had a good weekend working on the K1 with a good turnout both days (8 on Saturday and 7 on Sunday) and resultant steady progress being made. The boiler is now fully prepared for its annual cold exam and the leading coupled wheel set ready to come out. West Coast will put the loco over the wheeldrops and remove the wheelset this week. Good progress was also made with a number of other "smaller" jobs.

We had hoped that our boiler insurance company would allow the permanent repair to the firebox outer wrapper to be deferred until next year but we have been unable to agree this. We have therefore agreed the extent of plate work to be replaced and are currently in the process of agreeing the appropriate specs and procedures. West Coast will be carrying out the repair work on our behalf and this should commence very shortly.

There will be no mid week working party this week but I am hoping to organise Tuesday working parties from next week. There will certainly be a working party this coming Saturday so of you are available for ether Saturday or Tuesday (both would be even better) then please let me know.

 

 

9th January

Print

We had a good day on Saturday with con rods and coupling rods removed from both sides, the concrete arch removed and cleared away and the back head valve winter maintenance almost completed.

There will be no mid week working party this week but we are working both days this coming weekend. Please let me know if you would like to come along either day if you have not already done so.

In addition to work on the loco at Carnforth we are also carrying out maintenance and decorating work to the coach. One particular area where we could do with some help is in acquiring a new cooker, getting it fitted and arranging the gas safety certification for the coach. If you are willing to take this on then please let me know.

 

 

4th January 2017

Print

Happy new year.

After the Christmas break work on the K1 will continue this Saturday when we will be carrying on stripping the loco in readiness for the leading and trailing coupled wheelsets removal. We also need to remove the RH back sands box - should be interesting!

We will be doing a full weekend on 14th/15th Jan - you could do Sat, Sun or both days as the co car will be returning to Darlington/Teesside on Saturday evening.

I would also like to start mid week working parties, one day per week from next week. If you are available to work mid week, either regularly or just occasionally then please let me know, specifying whether you would prefer to work Tuesdays or Thursdays (Wednesdays are out as the co car is required for Q6 working parties).

 

 

21st December

Print

We had a decent day on the K1 on Saturday with more progress on the winter maintenance and, significantly, a very encouraging ultrasonic test of the firebox outer wrapper with no indication of any deterioration of the repaired area or any signs of fracturing or grooving to the opposite side. Discussions are now under way with our insurers to agree how and when the permanent repair is to be undertaken.

We have another working party this Saturday when I hope to remove the con rods in readiness for the remettalling of the big ends and lifting blocks (which are to replaced this year).

 

8th December

Print

We had a good day on working on the K1 last Sunday. The boiler was washed out, the loco winterised and a few bits were removed in preparation for the work ahead.

We are going over on Saturday. The priority being to remove the components necessary for the firebox outer wrapper to be examined in the area of this seasons failure (and the corresponding area on the opposite side).

 

 


Page 15 of 16