J72 Overhaul Update March 2021

Monday, 22 March 2021 12:39 William Nutbrown
Print

69023 Boiler Inside View

Boiler

Close examination of the boiler components has revealed that they are in a much poorer condition than had been anticipated from what could be established before dismantling. Several more stays have been removed this week to confirm the condition of a wider area of the wrapper sides.

Ian Storey, Neal Woods, Paul Hutchinson and Richard Pearson have all viewed the boiler (though not simultaneously) to help inform the engineering decisions which are now required, before instructing NSEL on how to proceed.

A number of costed options for repair have been provided by NSEL. The financial implications for the overhaul are being worked through and will be considered by the Project Team and by the Board.

Two drawings have been obtained from the National Railway Museum. One of the later boiler diagram, as used on our locomotive, and one showing various fastenings on the boiler. These will help with the overhaul of the boiler, as they confirm the design size and thickness of the boiler plates.

Cylinder Block

The original cylinder block halves are now at South Lincs Foundry (SLF). Pattern-making will commence soon.

Mechanical

A further set of horn guides has been machined and one set of horn stays has been welded up and await machining to suit the horn guides.

 

NELPG needs to invest some £225,000 to steam Joem again and a ‘Set to Steam Again’ appeal has been launched for direct donations or sponsorships.

For more details of the appeal including the opportunity to sponsor specific elements of the overhaul click here

All donations will be gratefully received.  Please, if you can, support Joem’s much needed return to steam.